How long will a room addition project take from start to...
Mar 31, 2026
| Project Concept | Done by the GC, Architect and You | 1–3 Weeks |
| Planning | Done by the Architect | 2–4 Weeks |
| Plan Approval | Done by City Officials and other local authorities | 3–24 Weeks |
| Construction | Done by the home addition contractor | 12–24 Weeks |
Naturally the timeline highly depends on the scope of work and the different cities’ bureaucracy and workload at the specific time. In Los Angeles city for example, a small 300 SF master suite addition can be completed in 4 months from planning to construction. The same project in Burbank, Glendale, or even the County of Los Angeles can take 6–12 months.